QA/QC Kick Off Meeting

Planning & Scheduling

horiline spacer

Does the project understand the work scope of each site subcontractor and has it been defined in the project scheduling. This is especially important for the completion of As-Built Dossiers for project Turn Over Purposes.

vertline

Constuctability Items Identified

horiline

Has the Project Identified major constructability site issues that will impact upon the completion of the site quality inspections and subsequently delay the turn over of Quality Dossiers to the customer.

vertline

Procurement Inspection Activities

horiline

Has the Project Identified all sub contractors procured items that might not conform to the customers Technical Specifications? Have these items been identified on a procurement matrix and receipt inspections been coordinated prior to release for site use.

vertline

QC organisation Chart Defined

horiline

Does each subcontractor have a designated team of Quality Control Inspectors with organisation freedom to reject and accept nonconforming material? Do these inspectors have sufficient qualifications and experience to complete the scope of work.

vertline

Point of Contacts Defined

horiline

The Project QA/QC team must identify points of contacts with the customer ,Prime Contractor, Sub contractors and Third Party Inspection bodies on site to ensure timely completion of site inspections.

vertline

QC Inspection Plan Reviewed

horiline

All the site subcontractors must understand and implement their site approved Quality Control Inspection & Test Plan (QCIP) to ensure the inspection of the work is undertaken during process and with out any schedule delays.

vertline

Health & Safety of Radioactive Sources Reviewed

horiline

All subcontractors that use radiactive sources must be aware of the site safety procedures and emergency evacuation procedures.